Typical Condo Interior Design Timeline in Singapore

image

Condo renovation is rarely a one-step process. Whether you’re moving into a newly finished home or updating a resale condo, the interior design process consists of planning, coordination, and execution phases. Timelines also often stretch due to regulatory approvals, supplier delays, and the need for precise space planning in compact layouts. Having a clear view of what happens at each stage can prevent costly missteps and unrealistic expectations for homeowners working with interior designers.

Discover the typical project timeline for condo interior design in Singapore—from first consultation to move-in day.

Initial Consultation and Design Brief (1–2 Weeks)

The process starts with a consultation where interior designers gather information about the client’s lifestyle, budget, design preferences, and renovation goals. This stage is essential in establishing feasibility, defining the scope of work, and clarifying any site-specific limitations, such as condo regulations. Site visits are usually conducted to take accurate measurements. Some firms may also conduct a needs analysis to determine functional requirements, especially if the unit is for multi-generational living, home-based work, or rental purposes.

Concept Development and Mood Board Presentation (2–3 Weeks)

Based on the design brief, the designer prepares a mood board, proposed layout, and initial material palette. This stage may involve multiple revisions as clients align their aesthetic expectations with practicality and budget constraints. Interior designers often tailor layouts for space efficiency, addressing issues such as limited kitchen size, lack of built-in storage, or awkward corners. Once a general direction is approved, the project moves into technical planning.

Detailed Design and Material Selection (2–3 Weeks)

After the concept is approved, the designer develops detailed drawings for carpentry, electrical, lighting, plumbing, and ceiling works. These are supported by 3D renderings or digital walkthroughs, especially for larger-scale projects. Material selection, such as tiles, laminates, sanitary fittings, and lighting fixtures, takes place concurrently. This phase is critical as these details directly affect both aesthetics and construction timelines. Interior designers in Singapore must also prepare submissions for MCST (Management Corporation Strata Title) approval at this stage, which can take up to two weeks, depending on the condo.

Renovation and Site Work (5–8 Weeks)

Once approvals and selections are finalised, renovation begins. This phase includes demolition, hacking (if needed), electrical rewiring, plumbing, tiling, carpentry fabrication and installation, painting, and final fittings. MCST restrictions in condo interior design may limit working hours and noise levels, which can stretch timelines. Renovations usually begin with wet works (tiling and hacking) and move into dry works (carpentry and painting). Concurrently, built-in furniture, like wardrobes and kitchen cabinets, is fabricated off-site. Delays at this stage are typically caused by last-minute material changes or supply chain issues, especially for imported fixtures or custom elements.

Site Cleaning, Inspection, and Handover (1 Week)

After all construction is completed, professional cleaning takes place, followed by a detailed inspection by both the designer and client. Snagging works, such as correcting misaligned cabinet doors, retouching paint, or fixing minor plumbing leaks, are conducted before the official handover. Interior designers typically schedule a final walkthrough to ensure the renovation meets the agreed specifications. Warranty documentation and maintenance guides are also provided to the homeowner.

Post-Handover Adjustments (Optional, 1–2 Weeks)

While not always accounted for, many interior designers offer a post-handover period to address minor issues that surface after the client moves in. These may include door hinge adjustments, power socket replacements, or sealing touch-ups. This stage is also when feedback is collected and the project is officially closed.

Conclusion

A standard project for condo interior design in Singapore typically spans 10 to 16 weeks from consultation to handover, depending on complexity, approval processes, and material lead times. Homeowners working with experienced interior designers benefit from clearer coordination, reduced delays, and better adherence to timelines. Early engagement, prompt decision-making, and understanding of the upcoming phases all contribute to a smoother renovation journey.